Workshop Order Review

All 54 potential findings and 3 detected cycles were reviewed against the workshop files. All are false positives: (1) the 07↔07d and 05↔05b bidirectional cycles are caused by forward-reference/error-recovery links in Before You Start callouts parsed as prerequisite edges — not true circular dependencies; (2) the 02a↔side-quest-02-01 cycle is two parallel alternative setup paths, not a cycle; (3) the 54 missing_prerequisite_link findings flag side quests for not having back-links to step 02 setup, but by design the linear workshop path ensures environment setup is complete before any step that uses gh aw commands. No confirmed ordering problems were found; no issue should be created.